Phase 1

Survey

5 - 7 Days

Health & Safety Rams

Heat Production, District Network & Point of Use Verification

Phase 2

Decision Making

5 Weeks

Primary Report & Presentation

Design Meetings, Scope of Works Drawn Up & Agreed

Tender for Works Presented

Phase 3

Contract Awarded

Notification Sent Out

Procurement

Phase 4

Site Set Up

5 Days

Health & Safety CDM

Temporary Heating & Enabling Works

Phase 5

Main Works (Team 1)

8 Weeks

Plant Room Strip Out Back to Bare Walls

Plant Room Builders Work & Painting

Improvements, Control Upgrades and Metering in Residential & Communal Areas

Complete System-Testing, Certification & Commissioning

Phase 5

Main Works (Team 2)

8 Weeks

Improvements, Control Upgrades and Metering in Residential & Communal Areas

Complete System-Testing, Certification & Commissioning

Phase 6

Site Set Up

6 Days

Practical Completion and Site Handover

Show All

Please note – provided as an example only – this will be dependent on the size of scheme.